Thursday, September 30, 2010


Another successful Solar PV Install completed by the Jonas Crew today!
WOW...this one is on a 12 on 12 pitch roof! Lookin Good!

Wednesday, September 22, 2010


If you are currently using our CFN cardlock card for fueling you will be excited to hear that you will be converted over to a FleetWide Card which will give you access to over 31,000 sites. Go to http://www.jonasoil.com/ or http://www.cfnnet.com/ to check it out.


If you do not have a Jonas CFN card yet...Call us today to get signed up.


Your card makes it super convenient to gas up and go! Plus keeps track of your usage!

Sunday, September 5, 2010

Come see us at the Lake County Fair!





Wednesday, March 17, 2010

New video: One of our Windspire installs in action.

Friday, February 26, 2010

Saturday, February 13, 2010

Thanks John, we will be putting that SkyStream on a 60' pole. This installation will also use our new foundation system and will be complete in one day. This is unusual installation, most installs take at least two days, and three days on site is common.
We normally have to dig a hole, place the re-bar cage and pour concrete. We then wait 28 days for curing and then install the unit. We will place the unit on the base the same day, and call for and afternoon inspection.
In this case the location already has a disconnect and wiring in place for an old sign so we do not need a treanching inspection before we install the unit.
If you would like to visit the site, let me know.
Craig Wooster

Saturday, February 6, 2010

Hello everyone,

Here's a photo journal of our wind generator install at our Lower Lake location. We'll be posting some more pics and videos for you all to see in the coming weeks. We hope this will give you an idea of the general install process.